Project: Rehabilitation and Streetscape North Harden Street Phase II
Owner: City of Columbia, SC
Engineer: LPA (now Michael Baker International)
Description: This project involved the complete replacement and restoration of Harden St and Read St including 3,000 LF of 5×4 box culvert storm drainage, 1000 LF of 42” DIP Waterline installation and tie-in, 24” DIP Waterline tie-in, additional 8” thru 12” DIP Waterline and tie-ins, 8” thru 16” DIP gravity sewer installation, curb and gutter, landscaping, road widening, asphalt milling and resurfacing, new traffic signals, street lighting, and major traffic control measures.
Cost: $14,216,000
Time: 900 Days
Completed: June 2015